Mastering digital transformation projects is my very passion. I gathered good & bad practices from different industries, which I will be happy to share with you.
Roles:
Roles:
Project Lead | Solution Architect
Corner Stones:
14 Warehouse numbers (EWM Embedded
)
Duration ~2
years Design / Implement / GoLive & Hypercare
Part of an S/4 Transformation
Highlights:
Big Bang GoLive | 24/7 & Multisite | Hypercare team with up to 34 members
Integration: QM | TM | PP | MES (Non-Sap)
Complex Enhancements
Key Challnges:
L
ogitiscs business without SAP (EWM) know-how
Little SAP (EWM) know-how in the implementation team
Complex system landscape
(1) Process design draft (2) Business alignment & approval (3) Template implementation - (4) Variant localization (5) Internal testing (6) Business Handover
Roles:
Part Project Lead | Solution Architect
Corner Stones:
ECC ERP & EWM system landscape on LSP side
S/4 HANA system landscape on customer side
Duration ~1
year design / implement / test
Part of an S/4 Transformation
Highlights:
Comprehensive integration of an external warehouse management system
Close to standard LE-IDW interface
High process variety & complexity
Key Challenges:
Two implementation teams (Customer & LSP)
No process or system documentation on customer side
Roles:
Project Lead | Solution Architect
Corner Stones:
1 warehouse number (Decentral EWM on ECC)
2 automated storage systems
Duration ~1
year Design / Implement / GoLive & Hypercare
Highlights:
Application of the "API-Driven ABAP Development Concept"
Complex customer specific Fiori applications
Complex out of standard PP-Integration
Key Challenges:
Defined blue print (pre-project) basically useless
Little SAP (EWM) know-how in the implementation team
High degree of customer specific programming
(1) Rollout of the "API-Driven ABAP Development Framework" (1) Implementation of additionally required API elements (2) implementation of the customer specific layer (3) implementation of test programs & unit tests
Roles:
Functional Streamlead - Logistics
Corner Stones:
Corner Stones:
~ 40 Warehouses - 13 of which on EWM
Duration ~ 2
years (Localization only)
Highlights:
Project frozen without GoLive
High organizational complexity
Close to "Standard" S/4 implementation
Key Challenges:
GoLive in other regions problematic
"Global Template" mostly does not meet local requirements
Very stiff "Process Follows System Approach"
(1) As-Is process identification
(2) Global template fit check
(3) To-Be Process definition & d
ocumentation
(5) Gap identification
(1) Risk of inoperability
(2)
Budget
(3)
Difficult market situation